RCU HQ Offices & Business Park — AlUla
Block Works — Supply, Delivery & Installation · FT-CCC-URC-WALLS-2026-V04
CONTRACT EX-VAT
8,826,700 SAR
REV · V04
2026-05-02
MODULE 10

Cash-flow & S-curve

ADVANCE PAYMENT %
RETENTION %
PAYMENT LAG (MONTHS)
MONTHLY WEIGHT % (must sum to ~100; current Σ = 100.0%)
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
CUMULATIVE S-CURVE
M1M2M3M4M5M6M7M8M9M10-3.5M0.0M3.5M7.0M10.5M
  • Cum Cost
  • Cum Cash In
  • Cash Position
MONTHLY DETAIL
MonthWeight %Month CostCum CostMonth Revenue (net of retention)Cum Cash-InCash Position
M110.0857,491857,491838,537882,67025,179
M215.01,286,2372,143,7281,257,8051,721,207-422,521
M315.01,286,2373,429,9651,257,8052,979,011-450,954
M415.01,286,2374,716,2021,257,8054,236,816-479,386
M512.01,028,9905,745,1921,006,2445,494,621-250,571
M610.0857,4916,602,683838,5376,500,865-101,818
M78.0685,9937,288,677670,8297,339,40150,724
M87.0600,2447,888,920586,9768,010,230121,310
M95.0428,7468,317,666419,2688,597,206279,540
M103.0257,2478,574,914251,5619,016,474441,560