RCU HQ Offices & Business Park — AlUla
Block Works — Supply, Delivery & Installation · FT-CCC-URC-WALLS-2026-V04
CONTRACT EX-VAT
8,826,700 SAR
REV · V04
2026-05-02
MODULE 12

Reports & Export

EXECUTIVE SUMMARY (PRINT-READY)
RCU HQ Offices & Business Park — AlUla
Block Works — Supply, Delivery & Installation · FT-CCC-URC-WALLS-2026-V04 · 2026-05-02
Direct Cost (Mat + Log + Mp + Eq + Ind + Sub)7,866,893 SAR
+ Site OH (3%)236,007 SAR
+ HO OH (4%)314,676 SAR
+ Contingency (2%)157,338 SAR
= TOTAL COST8,574,914 SAR
CONTRACT EX-VAT8,826,700 SAR
FORECAST MARGIN251,786 SAR (+2.9%)